CCCCD 2002-2005 RENEWAL & REPLACEMENT PLAN

PROJECT FALL SPR/SUM FALL SPR/SUM FALL SPR/SUM
  2002 2003 2003 2004 2004 2005
             
Replace original roof   Apr-June        
A & B Wings - CPC   $295,000        
             
Replace HVAC- A & B Wings Sept-Jan          
CPC $1,032,000          
             
Replace Fire Alerting   Apr-June        
System - CPC   $200,000        
             
Replace/repair West & So. Oct-Dec          
parking lot concrete - CPC $80,000          
             
Replace broken sky-lites Sep-Dec          
SCC $30,000          
             
Replace carpet - remaining Sep-Dec          
classrooms - SCC $100,000          
             
Replace Carpet - Dec-Jan          
offices & suites - SCC $90,000          
             
Replace carpet Nursing Lab Dec-Jan          
asstd offices, Pike Hall-CPC $60,000          
             
Seal parking lot joints & Sep-Nov          
cracks - All Campuses $70,000          
             
Install voice notification with   Jan-Apr        
Fire System - PRC & CYC   $200,000        
             
             
Rebuild Marley HVAC   Jan-Mar        
Cooling towers - SCC   $50,000        
             
Rebuild HVAC Cooling   Jan-Mar        
Towers - CYC   $40,000        
             
Concrete Repair/Handicaped Sep-Oct          
Parking - CYC $23,000          
             
Restore/Refurb. Roof -   May-Jul        
CYC   $60,000        
             
Replace Drip Irrigation -   Jan-Mar        
PRC   $80,000        
             
Seal/Waterproof   Jun-Jul        
Windows & Walls CPC   $150,000        
             
Inst. Fire Alarm Strobes Sep-Nov          
All R/R - SCC $75,000          
             
Restore/Refurbish Roof -   May-Aug        
SCC   $100,000        
             
Chair-rail Wainscot Sep-Nov          
Hallways - CYC $50,000          
             
Repaint Alum Trim @   May-Jul        
Entrances - SCC   $45,000        
             
Upgrade Elevators       May-Jun    
CPC       $100,000    
             
Pave Overflow Parking       Jun-Jul    
CPC       $200,000    
             
Replace Carpet - Heritage     Sep-Dec      
& Founders - PRC     $360,000      
             
Replace HVAC Chillers &         Oct-Dec  
EMS - CYC         $175,000  
             
TOTALS $1,610,000 $1,220,000 $360,000 $300,000 $175,000 $0
             
Total - Fiscal 2002-2003   $2,830,000        
Total - Fiscal 2003-2004   $660,000        
Total - Fiscal 2004-2005   $175,000        
             
Grand Total - 3 Years   $3,665,000